Project- Evendale Commons Stream Restoration- Case Study

0

Courtesy of Environmental Remediation Contractor

ERC was hired as the General Contractor for the restoration of the Mill Creek by the Village of Evendale.  The scope of work included the construction of one (1) riffle, rock toe, buried grade control, grading, and all site restoration.  After mobilizing to the site ERC cleared and grubbed the entire site and then excavated 2,900 CY of earth.  In order to align the stream and to slope the stream banks ERC then imported over 1,525 tons of rock including various rip rap and native bed material.  The site was finished by planting trees and installing 574 live stakes.