Ringwood School - Case Study
Project: Classroom building Client: Ringwood School Completed: February 2015 Floor Area: 344m² Duration: 12 Weeks Value: £500,000 Turnkey service elements completed: Design Groundworks Manufacture Installation Service ...
-
Jewell Academy - Case Study
Client: Bournemouth Borough Council Completed: August 2014 Number of Modules: 78 Duration: 7 months Value: £2.6m Turnkey service elements completed: Design Groundworks Manufacture Delivery and installation Service connections ...
-
Royal Arthur Barracks - Case Study
Project Duration: 6 Weeks Completed: Spring 2014 Contract Value: £90,000 No of Modules: 2 Turnkey service elements completed: Design Groundworks Manufacture Installation Service Connections Access Facilities Modulek provided ...
-
Wormley Primary - Case Study
Project: Breakfast/After School Club Building Client: Wormley Primary School Completed: Summer 2014 Floor area: 95m² Duration: 6 weeks Value: £105,000 Turnkey service elements completed: Design Manufacture Delivery & ...
-
Springwood Campus - Case Study
Project: Springwood Campus Client: Bournemouth Borough Council Completed: December 2013 Floor area: 700m² Duration: 5 months Value: £1,700,000 Turnkey service elements completed: Design & Planning ...
-
Danes Hill School - Case Study
Project: Classroom building Client: Danes Hill School Completed: Summer 2013 Floor area: 800m² Duration: 6 weeks Value: £800,000 Turnkey service elements completed: Design Groundworks Manufacture Delivery and ...
-
Sure Start Nursery - Case Study
Project: Sure Start Nursery Client: Jungle Hut Preschool Completed: July 2010 Floor area: 80m2 Duration: 3 weeks Location: Marnhull, Dorset Value: £90,000 Turnkey service elements completed: Base ...